1. Activity Predecessors Duration (months)

A – 3

B – 2

C A 5

D A 3

E B, C 4

F B, C 2

 

 

 

 

2.

Activity Duration Predecessors

A 5 days None

B 4 days None

C 8 days A

D 11 days A, B

E 1 day C

F 1 day D

G 6 days E, F

H 4 days G

I 12 days G

J 2 days L

K 9 days I, J

L 4 days H

 

 

3.

Activity Predecessors Duration

A – 10

B A 8

C A 12

D C 0

E B, D 18

F E 16

 

 

 

 

 

 